Good progress being made at Art'otel Hoxton

Good progress is being made on the delivery of Art'otel Hoxton. In recent weeks, the temporary earth-retaining works has been completed, over 2000 cubic metres of clay has been removed and work has begun on installing the new temporary welfare grillage. Over the coming weeks and months, work will begin on completing the new 3 storey temporary welfare unit, constructing the foundation and drainage of the building and work will begin on constructing the buildings main core utilising the slip form method.